Skip to content

7 · Milestones and the timeline

What you will have done: put a fixed date on the calendar, given some work a start and an end, and read the picture that shows what has to happen before what.

Two different kinds of date

A due date on an item says when that piece of work should be finished. A milestone is not a piece of work at all: it is a date the business cares about, with a name. “Keys to Unit 7.” “First pallet ships.” Nothing hangs under a milestone, and a milestone without a date is refused, because the date is the whole of it.

The timeline draws both. Milestones sit in their own strip along the top, above every group, so a busy project can never push its own deadlines off the picture.

The walkthrough

1. Add a milestone

New item, kind Milestone, and give it a due date. It will not save without one.

2. Give the work dates

Open an item and fill in Due, and a start date if the work has a run rather than a deadline. Both are optional. An item with only one of them is drawn as a point on that day, not as a bar stretched to the edge of the screen, because the other end is genuinely unknown.

3. Open the Timeline

The screen opens on ten weeks: the two behind you and the eight ahead, snapped to whole weeks. Today is a vertical line.

The timeline: milestone diamonds along the top, epics as group headers, bars beneath, and an arrow between two of them

Work is grouped by epic. The epic’s own dates are drawn on its header row. Click the chevron to fold a group away.

4. Read the arrows

An arrow is drawn between two items when one has to happen before the other:

LinkWhat it meansHow it is drawn
blocksThe second cannot start until the first is done. Enforced: the board refuses the move.A solid arrow
precedesThe second follows the first. An order, not a rule. Nothing is enforced.A dashed arrow

An arrow needs both ends on the screen. If one end is folded away, filtered out, or outside the ten weeks, no arrow is drawn.

5. Drag a date

Drag the middle of a bar and both dates move together, keeping its length. Drag either end and only that end moves. An end dragged past the other end does nothing rather than turning the bar inside out.

Every drop writes one change to the item, carrying the version the screen was drawn from, so two people dragging the same bar cannot both win.

6. Narrow it

Sprint, Epic and Assignee at the top narrow what is drawn. They filter the picture, not the window: the ten weeks stay the ten weeks.

A worked example

Meridian Supply’s move has two dates that cannot slip.

  1. Priya adds two milestones: Keys to Unit 7 on 21 September, and First pallet ships from Unit 7 on 2 October. Both appear as diamonds along the top.
  2. She gives the lease a run from 2 to 18 September, and the racking quotes from 14 to 22 September.
  3. She links Order the mezzanine handrail as blocked by Sign the Unit 7 lease, and a solid arrow appears between them. The supplier needs eight weeks and will not take the order without a signed lease, which is now on the picture rather than in her head.
  4. The quotes slip by three days. She drags the bar and both its dates move; the arrow follows.

What can go wrong

The sentence on screenWhat happened, and what to do
Nothing here carries a date yet. Give an item a start or a due date, or add a milestone, and it appears on this timeline.The project has dates on nothing. Add one and the screen fills in.
a milestone must carry dueAtYou tried to save a milestone with no date. A milestone is its date.
This project has more dated items than one timeline draws. Narrow the window to see the rest.The project is larger than one timeline page. Use the Epic, Sprint and Assignee filters to cut it down.
Someone changed this first — reloadedSomebody moved the same bar. The screen has caught up; drag again if you still mean to.
An arrow you expected is not drawnBoth ends have to be on screen. Unfold the group, clear the filter, or check that both items carry dates inside the window.
Two items look linked but nothing stops the second startingThe link is precedes, which is an order rather than a rule. Use blocks if it should actually stop the work.
The window cannot be paged yet. The timeline always draws the same ten weeks around today, and there is no control on the screen to move it forward or back. Work that falls outside that window is not drawn, and the only way to change what is on screen is to change the dates. Long-range planning past two months is not something this screen can show today.

Confirm it worked: the milestone appears as a diamond in the top strip on the day you gave it, and each item you dated has a bar that starts and ends where you said.

Last updated on